CleanSpark, Inc. (Nasdaq: CLSK) reported on November 24, 2026, that 86 MW of grid-connected power is currently energized at its site in Washington, Georgia, as the company continues shifting its Georgia portfolio toward AI data center use. The update came in the company's fiscal fourth quarter and full year 2026 results.
At Washington, CleanSpark said it submitted a high-density line study seeking to raise available power to 500 MW. According to the company, preliminary results suggest the transmission system could support up to 500 MW over several years, although that capacity has not been confirmed. CleanSpark also said it acquired 500 adjacent acres for a future AI data center campus.
At its Sandersville, Georgia, project, CleanSpark said it holds a 20-year, $6.6 billion triple-net lease with a tenant it describes as high investment grade. The company reported that $2.276 billion of 7.875% senior secured notes due 2031 fully fund development, that all material building and development permits have been obtained, and that construction is on schedule for a first planned data hall in November 2027. A turnkey, lump-sum development contract is in place, and long-lead equipment has been prepaid, the company said.
For the fiscal fourth quarter, CleanSpark reported revenue of $120.9 million, down 46% from a year earlier, and net income of $9.8 million. Full-year revenue was $576.5 million, down 25%, with a net loss of $987.1 million.
The company also said tenant exclusivity has expired at its Sealy and Brazoria sites in Texas, which hold conditional ERCOT designations totaling 585 MW, and that commercialization efforts continue with the Sandersville tenant and other parties.
Source: Stock Titan -- https://www.stocktitan.net/news/CLSK/clean-spark-reports-fiscal-fourth-quarter-and-full-year-2026-jbrzj8ijpq4q.html