Power demand from data centers has risen an average of 19% a year since 2000, while U.S. grid capacity has expanded about 2% a year, according to an analysis by insurance broker Howden reported by Fortune on November 22. Data centers used about 5% of U.S. grid capacity in 2025.
Howden estimates that to hold that share through 2030 at current growth rates, data centers would have to source up to 58% of their power off the grid, or roughly 110 gigawatts, a level the firm itself considers unlikely. Lawrence Berkeley National Laboratory projects that data centers could account for up to 12% of U.S. electricity use by 2028, compared with 1.9% in 2018.
Rob Gramlich, president of consulting firm Grid Strategies, has said grid expansion requires "deliberate study and planning" that can take years, and that utilities "got out of practice" building new infrastructure after roughly 25 years of little demand growth. Kathryn Burke of insurance firm Marsh expects around 50% to 60% of data center projects to miss developers' one to two year timelines.
Cornell researchers Cheng Feng and Fengqi You, writing in Nature Energy, found that data centers raised 2025 wholesale prices by nearly 20% in California's southern Bay Area and close to 17% around Dallas and Fort Worth. Across four grids studied, data centers paid 38% of growth related infrastructure costs in 2025, or $3.12 billion of $8.25 billion.
Self supplied power is drawing attention. In August, Delaware enacted a requirement that large users such as data centers produce or secure all of their power within 10 years of starting operations. BloombergNEF has tracked 181 gigawatts of announced gas fired generation tied to data centers, more than 90% of it in the United States.
Source: Fortune -- https://fortune.com/2026/11/22/ai-data-centers-power-grid-capacity/