A Tennessee Valley Authority annual report filed with the Securities and Exchange Commission references a data center power agreement worth about $1.7 billion in aggregate payments, according to a November 24, 2026, report by WVLT in Knoxville. It would be the first agreement to fall under the federal utility's new data center rates.
According to the filing as described by WVLT, TVA would receive a $31 million primary payment when the agreement is finalized, with the remainder paid in 59 installments. The filing states that TVA expects to record the first $31 million payment in November.
In September, TVA announced that data centers would pay $1.5 million per megawatt for load above five megawatts. Using that rate, WVLT calculated that the facility could have a power draw of roughly 1,100 megawatts. TVA spokesperson Scott Brooks confirmed the math but declined to confirm the facility's capacity. "Your understanding is correct, but we wouldn't speculate on the capacity," Brooks said.
The customer's name and the project's location were not disclosed, other than that the facility would be within TVA's service area. Brooks said the utility does not disclose confidential business information regarding individual customers or prospective economic development projects, and that it protects commercially sensitive information while working with customers, local power companies and economic development partners.
The filing does not say when construction could begin. TVA is the largest public power provider in the United States, and the deal adds to a series of large-load agreements that utilities across the Southeast have signed or proposed as data center developers seek long-term electricity supply.
Source: WVLT -- https://wvlt.tv/2026/11/24/tennessee-valley-authority-filing-references-17-billion-data-center-deal