A new report from Columbia University's Center on Global Energy Policy identifies three main reasons that construction of Plant Vogtle Units 3 and 4 in Waynesboro, Georgia, ran behind schedule, according to coverage by the American Nuclear Society's Nuclear Newswire. The two Westinghouse AP1000 units entered commercial operation in 2023 and 2024 and are the most recently completed reactors in the United States.
Authors Matt Bowen and Rama Ponangi reviewed about 1,200 pages of testimony and monitoring reports from William Jacobs Jr., the project's independent construction monitor, who filed semiannual reports from 2009 through 2023. Jacobs said early in the project that he lacked adequate access to documents, and large portions of his testimony are redacted.
The first cause the report lists is the absence of a realistic integrated project schedule, a concern the monitor first examined in 2012 and raised through his final report. The second is a failure to meet Nuclear Regulatory Commission quality assurance requirements, as the parties to the 2008 engineering, procurement and construction agreement were not initially prepared. A Louisiana fabrication facility with no prior nuclear grade manufacturing experience caused lasting problems.
The third cause is an incomplete and changing AP1000 design. Only 40 percent of plant engineering documents had been issued when the combined construction and operating license was granted in 2012, and later design changes created licensing issues. Other factors included missed productivity targets, heavy use of a partial release for test process, and poor sequencing of work.
The report's lessons call for a mature design before construction begins, a complete Level 3 integrated project schedule with realistic inputs, strong early quality control, and suppliers with nuclear grade manufacturing experience.