A new small modular reactor carries a total overnight capital cost of $9,831 per kilowatt in 2025 dollars, compared with $8,255 per kilowatt for a large light water reactor, according to the US Energy Information Administration's assumptions for its Annual Energy Outlook 2026, published in April 2026.
The EIA cost table models a 2,156 megawatt light water reactor plant and a 480 megawatt SMR plant, with both technologies first available in 2031 and a six year lead time. Base overnight costs are $7,862 per kilowatt for the large reactor and $8,937 per kilowatt for the SMR. EIA then applies a technological optimism factor of 1.05 to the large reactor and 1.10 to the SMR. The agency says that factor reflects the tendency to underestimate costs for the first units of a new design.
Operating cost assumptions point in different directions. EIA lists fixed operations and maintenance costs of $127.62 per kilowatt-year for the SMR, below $163.40 for the large reactor. Variable operations and maintenance costs are $3.32 per megawatt-hour for the SMR and $2.62 for the large unit.
Costs vary by region. Across the 25 electricity market regions, the average total overnight cost is $8,538 per kilowatt for large reactors and $10,061 for SMRs. In the SERC Southeast region, EIA puts the figures at $8,295 for large reactors and $9,768 for SMRs. The Texas region shows $7,866 and $9,366, while the Tennessee Valley region shows $8,630 and $9,981.
The overnight figures include project contingency but exclude interest charges during construction. The cost and performance estimates draw on a January 2024 study by Sargent & Lundy.
Source: U.S. Energy Information Administration -- https://www.eia.gov/Outlooks/Aeo/assumptions/pdf/EMM_Assumptions.pdf