Dow and X-energy are moving into the next phase of their Long Mott small modular reactor project in Seadrift, Texas, after receiving a Nuclear Regulatory Commission construction permit, POWER Magazine reported. The plant would use four Xe-100 high temperature gas cooled reactors.

Dow is expected to consider a preliminary investment decision in 2027, with a separate final investment decision required before full scale nuclear construction. Dow originally envisioned starting construction in 2026 and finishing by the end of the decade. The company now projects construction could begin later this decade, with startup in the early 2030s. The permit sets July 1, 2033, as the earliest completion date and December 31, 2033, as the latest.

Dow executive Edward Stones said the company will keep evaluating the project on competitiveness, execution readiness, and capital affordability before any construction decision is made. X-energy CEO Clay Sell said the final reactor design will be finished before construction begins. X-energy plans to file an operating license application about two years before commissioning.

No overall construction cost estimate has been disclosed. Under the Department of Energy's Advanced Reactor Demonstration Program, cumulative reimbursements to X-energy reached $618 million through September 2026.

The supply chain is taking shape. Doosan Enerbility has reserved capacity for 16 sets of reactor and steam generator pressure vessels, covering the four Long Mott units and up to 12 at Energy Northwest's Cascade project in Washington. A NextEra Energy Resources subsidiary was selected to operate the plant. X-energy's TRISO-X unit completed the shell of its TX-1 fuel facility in Oak Ridge, Tennessee, which is designed to produce about 700,000 fuel pebbles a year.

Source: POWER Magazine -- https://www.powermag.com/landmark-nrc-construction-permit-ushers-in-next-phase-for-dows-xe-100-htgr-nuclear-project/