The U.S. Nuclear Regulatory Commission has extended its review schedule for Project IKE, the centrifuge uranium enrichment facility that Orano Enrichment USA plans to build in Oak Ridge, Tennessee, World Nuclear News reported on November 16.
The NRC had planned an accelerated 12-month review with completion targeted for April 30, 2027. In a letter dated October 27, 2026, the agency set a new target of June 20, 2027. Orano selected Oak Ridge as its preferred site in September 2024, submitted its environmental report in January and filed its license application in March. The NRC accepted the application for review earlier this year.
Two factors drove the change, according to the report. Orano asked for additional time to respond to the NRC's Requests for Additional Information. The NRC also said Orano had not provided a crosswalk document comparing Project IKE with the previously approved Eagle Rock license. The agency noted that the two applications have limited similarities that could help speed the review.
Orano expects to submit all of its responses to the information requests by December 14, 2026. An Orano spokesperson said the longer review is not expected to delay enrichment operations at the Tennessee site, which the company expects to begin in 2031.
The project is part of a wider effort to rebuild domestic uranium enrichment capacity in the United States, which supplies fuel for the country's fleet of commercial reactors. East Tennessee already hosts several federal and private nuclear facilities centered on the Oak Ridge area, and the Orano plant would add commercial enrichment work to that cluster.
Source: World Nuclear News -- https://world-nuclear-news.org/articles/nrc-extends-project-ike-review-timetable