enCore Energy, a uranium producer operating in South Texas, reported third quarter 2026 revenue of $16.7 million, up 88% from $8.9 million a year earlier. The company delivered 200,000 pounds of uranium concentrate in the quarter, compared with 130,000 pounds in the third quarter of 2025, at an average realized price of about $83.46 per pound.

Cost of sales reached $17.4 million, or $87.22 per pound, which the company attributed mainly to a higher share of purchased uranium in its deliveries. That produced a gross loss of $0.8 million against a $3.9 million gross profit in the same period last year. The net loss attributable to enCore was $33.9 million, or $0.17 per share, including a $17.0 million realized loss tied to the distribution of Verdera Energy shares to shareholders.

For the first nine months of 2026, revenue rose to $50.7 million from $30.8 million. Of the 685,000 pounds sold, 560,000 were purchased and 125,000 were extracted from the company's own operations.

On the operating side, the Wellfield 3 Extension at the Alta Mesa project in South Texas is ready and awaiting final regulatory approval, with extraction expected before the end of 2026. Wellfield 8 is in development for early 2027, and the first phase of the Upper Spring Creek facility in Texas is complete. In South Dakota, the Dewey-Burdock project received Bureau of Land Management approval of its plan of operations in June, and state permitting continues.

In July the company reduced its workforce by about 20%, citing South Texas permitting delays. CEO Rich Little said, "2026 has been a challenging year for enCore."

Source: Investing News Network -- https://investingnews.com/encore-energy-reports-third-quarter-2026-financial-and-operating-results/